280-288
Harold’s Cross Road

A new development by Anthony Neville Homes

Programme

The demolition works are complete.

Piling – will start 12th March and complete mid-April.

Groundworks – will commence mid-April.

Access to the site

Piling to the basement is about to start on 12th March.

Preparation for these piling works is underway.

Access onto the site for these works will now move to the new gate 2 located on Harold’s Cross Road (see the sketch below).

This will become the primary access route onto the site until approximately October 2020. We do expect to use Fitzpatrick’s Lane for light vehicles, however this will be limited. Please note that the piling rig is delivered on an Abnormal Load and therefore this is done out of normal hours.

The rig will be delivered to site on Thursday morning at approximately 06h00. We will make all attempts to reduce the noise during this delivery.

Click to enlarge image.

Hoarding

Netwatch Camera Security will be placed around the perimeter of the site on the hoarding line with audible alarms issued to any intruders.

Click to enlarge image.

Working hours

The site will be open and operational during the following hours:

Weekdays – 07h00 to 18h00

Saturdays – 08h00 to 14h00

Works in March–May 2020

Demolition works are now complete.

The piling operation will now start and be complete in mid-April, following which further groundworks for the basement will start.

This will be ongoing for the full month of April and into May.

Contact

Please contact the following should you have any queries or complaints

John Nicol

Snr Contracts Manager

Please complete the contact form below to subscribe for future updates

Web design by Southeast Digital